You won the grant. Here is how to run it: a 30-day setup, a compliance calendar and a clean closeout
Short answer. Managing a grant means four jobs on a schedule. Set the grant up in its first month. Put every due date on one calendar with one named owner.
Check money and results once a month.
Close out inside the funder's window, which for federal awards is 120 calendar days after the end date (90 days if you receive the money through a state, a city or another organization).
Your award agreement beats any guide, this one included, so read it first.
Checked 13 November 2026. Federal rules below come from 2 CFR Part 200 and apply only to federal awards, including federal money passed to you through a state, a city or another organization. Foundations follow their own agreements. Not legal or accounting advice.
Days 1 to 30: the setup checklist
The days are our suggestion. The tasks are what you will need in place before the first report.
| By day | Task | Owner |
|---|---|---|
| 3 | Read the whole agreement and fill in the award sheet below | Grants owner |
| 5 | Email the funder about anything unclear. Save the reply | Grants owner |
| 7 | Give the grant its own code in your books, so every cost charged to it comes out in one report | Finance |
| 7 | Open the grant folder: agreement, approved budget, application, funder emails, every report you send | Grants owner |
| 10 | Decide how staff paid from the grant record their time | Finance and program lead |
| 14 | Kickoff with everyone who spends or reports: what the grant pays for, what it does not, which numbers to collect from day one | Program lead |
| 14 | Put every date on the calendar with an owner | Grants owner |
| 30 | Hold the first monthly review | Everyone above |
The award sheet. One page per grant, at the front of the folder.
| Question | Answer |
|---|---|
| Amount, start date, end date | ____ |
| Funder contact (name, email) | ____ |
| Reports owed: type, period covered, due date | ____ |
| How you get paid: advance or reimbursement, and how to ask | ____ |
| Match required: amount, and what counts | ____ |
| Changes that need the funder's written approval | ____ |
| Capped or restricted budget lines | ____ |
| Indirect cost rate allowed | ____ |
| Special conditions | ____ |
| Can unspent money carry over? | ____ |
| How long you must keep records | ____ |
Three federal points to settle in this month:
- Time records. "Charges to Federal awards for salaries and wages must be based on records that accurately reflect the work performed" (2 CFR 200.430(g)(1)). A budget estimate alone does not count. Pick the timesheet method now, not at report time.
- Budget against actual, per award. Your financial system must allow "Comparison of expenditures with budget amounts for each Federal award" (200.302(b)(5)). That is what the separate code is for.
- Cash. The rule's default is advance payment if your written procedures and financial system meet its standards (200.305(b)(1)). Reimbursement is preferred in listed cases, including when you request it or cannot meet those standards (200.305(b)(3)). If you will be reimbursed, plan how you will cover costs until the money arrives.
Who does what
Give every job one name. "The team" is not an owner.
| Job | Grants owner | Program lead | Finance | Executive director |
|---|---|---|---|---|
| Keep the calendar and the folder | Does | ____ | ____ | ____ |
| Collect program numbers | Checks | Does | ____ | ____ |
| Code costs and keep time records | ____ | Approves staff time | Does | ____ |
| Monthly budget against actual | Reviews | Explains variances | Does | ____ |
| Write the narrative report | Does | Supplies facts | ____ | Approves |
| Prepare and sign the financial report | Checks it matches the narrative | ____ | Does | Signs |
| Ask the funder for a change | Does | Says why | Prices it | Approves |
| Submit and save the confirmation | Does | ____ | ____ | ____ |
| Closeout | Leads | Final numbers | Final reconciliation | Signs |
In a small shop one person may fill two columns. That is fine as long as each row still has one name.
Grant loads get big: one development director on r/nonprofit (post 1wh7wfz, 15 September 2026) described having "juggled three federal, two state, and 47 private grants".
Nobody can hold that many dates in their head.
The compliance calendar
Fill in one row for every date in the agreement. Then add a "start work" date about a month before each report (our suggestion).
| Due date | What is due | To whom | Owner | Start work on |
|---|---|---|---|---|
| ____ | ____ | ____ | ____ | ____ |
If the award follows the Uniform Guidance and your agreement sets no other date, these are the default clocks:
| What | Deadline | Rule |
|---|---|---|
| Quarterly or semiannual financial and performance reports | No later than 30 calendar days after the period | 200.328(c), 200.329(c)(1) |
| Annual reports | No later than 90 calendar days after the period | 200.328(c), 200.329(c)(1) |
| Request for a no-cost extension | At least 10 calendar days before the end date | 200.308(f)(10), (g)(2) |
| All final reports | No later than 120 calendar days after the end date (90 for a subrecipient reporting to a pass-through entity) | 200.344(b) |
| Pay all obligations | Same 120 days (90 for a subrecipient) | 200.344(c) |
| Keep records | Three years from submitting the final financial report, longer if an audit, claim or litigation is open | 200.334, 200.334(a) |
| Single or program-specific audit | Required for any fiscal year you spend $1,000,000 or more in federal awards | 200.501(a) |
The monthly review
One meeting per grant, about half an hour, same agenda every time.
- Spending pace. Budget against actual, line by line. If you are six months into a twelve-month grant and have spent 30 percent, say why (invented numbers, to show the arithmetic).
- Wrong charges. Anything coded to the grant that does not belong there moves off now.
- Time records. In and approved for every person charged.
- Results. Each number against the target in the application.
- Match. This month's match recorded with its proof.
- News for the funder. Federal recipients must tell the agency between reports about "problems, delays, or adverse conditions" that will affect milestones or objectives, with a corrective action plan (200.329(e)). Good surprises count too.
- Next 90 days. What is due, and whose name is on it.
Write three lines in the grant folder: what changed, what you decided, who does what next.
Changing the budget or the plan
You may read that federal grantees can move up to 10 percent between budget lines without asking. The rule does not say that.
2 CFR 200.308(i) says the agency "may also, at its option, restrict the transfer of funds among direct cost categories" when two things are both true: the federal share is above the simplified acquisition threshold, and transfers add up to more than 10 percent of the total budget.
2 CFR 200.1 points to the Federal Acquisition Regulation for that threshold, which FAR 2.101 sets at $350,000 (read 13 November 2026).
So 10 percent is a limit an agency can choose to apply to larger awards. Your award terms say whether it does.
Whatever the size, 200.308(f) requires prior written approval for these changes, among others:
- a change in scope or objectives
- a change in key people named in the award
- the project director away more than three months, or cutting time on the award by 25 percent
- moving participant support money to other categories
- subawards that were not in the approved award
- a change in the total cost sharing
- needing more federal money
- a no-cost extension beyond any one-time extension the award allows
How to ask: in writing, using the same budget format as your application unless the agency approved another (200.308(c)).
The agency "should notify" you within 30 days or tell you in writing when to expect a decision (200.308(d)). Do not act until you have the approval in the folder.
For a foundation grant, the agreement sets the rules; if it says nothing, ask your program officer before you move money.
Closeout: count back from the end date
| When | What |
|---|---|
| 90 days before the end | Compare spending to budget. Decide whether you need more time. |
| At least 10 days before the end | Send any no-cost extension request or notice (200.308) |
| 60 days before the end | Start the final narrative. Collect final program numbers |
| End date | Stop new costs. Only administrative closeout costs may run until the final report is due (200.403(h)) |
| Within 120 days after | Pay every obligation, submit every final report, and "promptly refund any unobligated funds" you are not allowed to keep (200.344(b), (c), (e)) |
| After the final financial report | Write the keep-until date on the folder: three years from that submission (200.334) |
Missing closeout has teeth. If final reports never arrive, the agency must report your "material failure to comply" in SAM.gov (200.344(i)).
Under 200.339, when specific conditions cannot fix the problem, it may also withhold payments, disallow costs, suspend or end the award, or hold back new funding.
Where Nonprofit Grant Tracker fits
Nonprofit Grant Tracker is free, and we make it. It sets itself up from your organization's public tax filing (Form 990).
You add each report, renewal and follow-up with a due date, an owner and a status. The reports page lists every report you owe, when it is due and what goes in it.
A "next 90 days" view matches step 7 of the monthly review, and a "who holds what" page shows open grants and reports by the name on each.
Know its limits. It does not notify anyone, and its own reminders show only while the page is open, so export every date to your own calendar (.ics).
It runs in one browser on one computer, and your data stays there; we do not see it. To share, export a backup and import it on the other computer.
Two people cannot edit one live record. Keep budget against actual in your accounting system, with finance.
If you would rather have a team write the applications and take the rest of the busywork off your plate, that is what we do at One Giant Leap.
What this article cannot tell you
- Your award agreement can change every federal default above. Federal agencies also add their own terms. Read yours.
- Foundation, state and corporate grants follow their own agreements. The checklist and review still work; the federal clocks may not apply.
- The day counts in the setup checklist, the monthly agenda and the closeout count-back are our method, not research results. We found no study that measures them.
- We read the rules on 13 November 2026. The Uniform Guidance and the FAR threshold change over time.
- We built Nonprofit Grant Tracker, so we cannot judge it neutrally.
- This is not legal or accounting advice.
Sources (read 13 November 2026)
Rule text read on Cornell LII; key quotes checked against eCFR, title 2 up to date as of 12 November 2026.
- 2 CFR 200.302, financial management: https://www.law.cornell.edu/cfr/text/2/200.302
- 2 CFR 200.305, payment: https://www.law.cornell.edu/cfr/text/2/200.305
- 2 CFR 200.308, revision of budget and program plans: https://www.law.cornell.edu/cfr/text/2/200.308
- 2 CFR 200.328, financial reporting: https://www.law.cornell.edu/cfr/text/2/200.328
- 2 CFR 200.329, performance reporting: https://www.law.cornell.edu/cfr/text/2/200.329
- 2 CFR 200.334, record retention: https://www.law.cornell.edu/cfr/text/2/200.334
- 2 CFR 200.339, remedies for noncompliance: https://www.law.cornell.edu/cfr/text/2/200.339
- 2 CFR 200.344, closeout: https://www.law.cornell.edu/cfr/text/2/200.344
- 2 CFR 200.403, factors affecting allowability of costs: https://www.law.cornell.edu/cfr/text/2/200.403
- 2 CFR 200.430, compensation and personal services: https://www.law.cornell.edu/cfr/text/2/200.430
- 2 CFR 200.501, audit requirements: https://www.law.cornell.edu/cfr/text/2/200.501
- 2 CFR 200.1, definitions (simplified acquisition threshold): https://www.law.cornell.edu/cfr/text/2/200.1
- FAR 2.101, simplified acquisition threshold: https://www.acquisition.gov/far/2.101
- eCFR title 2 status ("up to date as of" date): https://www.ecfr.gov/api/versioner/v1/titles.json
- r/nonprofit post 1wh7wfz, 15 September 2026 (our 13 Nov 2026 study of 33,717 Reddit posts)
- Nonprofit Grant Tracker, One Giant Leap: product page text, 13 Nov 2026